Olskroken is one of the country's busiest railway junctions. A conversion to grade-separated railway tracks is necessary to increase accessibility and operational reliability for all train traffic to and from Gothenburg.
The Swedish Transport Administration is the client, Peab is the contractor and Atritechar has been brought into the project to measure the free space on site to ensure that the project is built according to current requirements.
The project involves the construction of new tracks to separate freight traffic from passenger traffic. A reconstruction in Olskroken so that the railway tracks cross each other at different levels will increase capacity and increase accessibility and operational safety for all train traffic to and from the connecting tracks. The contract extends over an area of approximately two kilometers and involves the construction of tracks, bridges and other buildings for both passenger and freight trains in a complex and heavily trafficked track environment.
Atritec was commissioned to carry out a Formula (obstacle-free) measurement to specifically investigate the position of two bridge foundations in relation to the tracks. The bridge foundations were under construction and thanks to Atritec's measurement, it was ensured that the bridge foundations would not restrict the free space of the tracks even before completion. In this way, a costly re-design and reconstruction could be avoided.
“With our assistance, the project has been able to ensure at an early stage that it is built according to specification. It has been possible to control the construction in stages, thereby reducing the risk of delays within the project.” -Andreas Nordin, CTO at Atritec.
Atritec offers, using innovative technology, a safe, fast and cost-effective way to perform Formula & Track Distance Measurement. When a measurement has been performed, a clear verification report is quickly created that provides a clear picture of the current situation and makes any follow-up easy. Atritec then handles all delivery and updating of the Swedish Transport Administration's BIS system and ensures that all involved parties receive the information they need on time.
"We take care of all aspects from start to finish, which contributes to efficient work for contractors. Our industry experience and the fact that we are at the forefront of technical development mean that we can not only deliver time- and cost-effective Formula measurements. It also enables us to create added value for the customer in most cases by using the same measurement data for several different purposes." - Andreas Nordin, CTO at Atritec.